21st July 2020 |
Jamie Barrett |
Reading Time: 4minutes
Producing an OCE for an initial Development Appraisal or to determine Site Residual Value
In this article, we looked at how effective cost management was dependent on the consistent use of the correct terms throughout a project. This included what an order of cost estimate is and what information is needed to prepare one.
The order of cost estimate is such an important tool used to assess the affordability of a proposed development, that it’s worth looking at in more detail.
What is an Order of Cost Estimate?
Order of Cost Estimate (OCE) is a term using by the Royal
Institution of Chartered Surveyors (RICS) under the New Rules of Measurement,
specifically NRM 1 for capital building projects.
An OCE is prepared as an intrinsic part of RIBA Stage 1: Preparation and Briefing. The purpose is to establish if the proposed building project is affordable and if so, to set a realistic cost limit for the development project.
The cost limit is the maximum amount that the employer is prepared to spend in relation to the project.
NRM1 recognises three estimating methods. These are:
floor area method;
function unit method (i.e. per house type);
elemental method.
The key constituent parts of an Order of Cost Estimate are:
Facilitating Works (i.e. demolition of existing
buildings, contamination removal etc.)
Building Works
Main Contractor Preliminaries / Construction
Management Site Services and Facilities
Main Contractor’s OH&P or Construction
Management Fee
Project and Design Team Fees
Other Development Costs (i.e. land acquisition
costs, planning fees, building control fees, CIL contributions etc.)
Risk Allowances / Contingency
Tender and Construction Inflation
Now you have a good understanding of what an Order of Cost Estimate is, let’s look at a worked example.
Order of Cost Estimate Worked Example
A developer is looking to construct 12 houses in a linear
design with a mix of four- and five-bedroom detached homes in Chelmsford, Essex.
The Gross Internal Area of the 12 units is 2,700m2 and the
overall site is 13,000m2.
The developer is looking to achieve a high price for each property contributing to a £8.7m Gross Development Value (read more about that here).
The properties have integral garages and driveways for two
cars to the front of the property. The remaining frontage and rear gardens are
soft landscaped.
There is an access road of approximately 100m, which runs
parallel to a main road and is connected by a small bell-mouthed entrance.
The site was previously used for agricultural use and comprises eight outbuildings, incoming electricity and water. The site is relatively flat but is overgrown with grass, brambles and shrubbery.
In order to work out a ‘rough’ order of cost estimate that
will inform a development appraisal for either meeting funding criteria, or for
a selling agent to determine the residual site value, the area method is
adopted.
The following worked example base date is the second quarter of 2020 (2Q20) with no allowance for tender inflation, construction inflation or value-added tax (VAT). Due to the higher specification finishes required, upper quartile cost data for Chelmsford, Essex has been used.
Ref
Item
Total
£/m2
£/ft2
£
£
£
1
Facilitating Works Estimate
Demolition of eight outbuildings, allowance @ £5k per building
40,000
14.81
1.38
Strip vegetation and level site
5,000
1.85
0.17
2
Building Works Estimate
Plots 1 – 12 (using upper quartile data), 2700m2, base date 2Q20
3,847,500
1,425.00
132.39
Access Road 6m wide, 100m long
81,180
30.07
2.79
E/O for NR&SWA to connect entrance
10,000
3.70
0.34
SUDs and drainage
40,000
14.81
1.38
Hard and soft landscaping
120,000
44.44
4.12
3
Site Facilities and Site Services Estimate
Construction Management Preliminaries
@ 12%
497,242
184.16
17.11
Sub Total
4,640,922
1,718.86
159.68
4
Construction Management Fee Estimate
(or alternatively use Main Contractor overhead & profit) @ 5%
232,046
85.94
7.98
Works Cost Estimate
4,872,968
1,804.80
167.66
5
Project / Design Team Fees Estimate
Project/Design Team Fees plus surveys @ 9%
438,567
162.43
15.09
Sub Total
5,311,535
1,967.23
182.75
6
Other Development Cost Estimate
(excluded – to be included in Developers appraisal i.e. building
warranty, S106, etc.)
Exc
Exc
Exc
Base Cost Estimate
5,311,535
1,967.23
182.75
7
Risk Allowances Estimate
Design Development Risk Estimate
265,577
98.36
9.14
Construction Risk Estimate
265,577
98.36
9.14
Employer Change Risk Estimate
Exc
Exc
Exc
Employer Other Risk Estimate
Exc
Exc
Exc
Cost Limit (excluding Inflation and VAT)
5,842,689
2163.95
201.03
What does this example of an Order of Cost Estimate mean?
Based on the information available at this early stage, the
cost limit for the planned development in our example is £5.85m (rounded).
However, it’s important to remember that there is no
provision for inflation and a number of exclusions have been noted. This means
that the actual cost limit may
be higher, and more accurate figures will be developed as the project is
developed.
Exclusions such as those shown in Section 6 of the Order of Cost Estimate example, are largely in the control of the developer/employer and should be included in the overall development appraisal. More control can be exercised over the exclusions noted in Section 7 (this section may be more commonly recognised to a lay-person as the contingency) although allowances must still be allowed.
Summary
A comprehensive Order of Cost Estimate, prepared during the
early stages of establishing project viability, will provide a reliable cost
limit for the project and allow the developer to demonstrate the margin that
can be achieved.
With robust allowances being made for abnormals, design development and issues such as unavoidable delays, the developer will be able to enter into the project with the full backing of well-informed lenders and/or investors.
For help preparing an Order of Cost Estimate to get your residential development project off to a strong start, call 023 80405073.
15th January 2025 |
Jamie Barrett Reading Time: 3minutes
The Construction (Design and Management) (CDM) Regulations were introduced in 2015. They require organisations and employees to have the competency to carry out construction...
28th November 2024 |
Liz Clarke Reading Time: 6minutes
Tendering is accepted as an essential part of the construction industry, yet, in our experience, the process is riddled with inefficiencies that ultimately increase...
22nd November 2024 |
Liz Clarke Reading Time: 4minutes
A successful construction project doesn’t happen by chance — it’s the result of clear thinking, detailed planning, and excellent collaboration between all parties involved....
20th November 2024 |
Liz Clarke Reading Time: 4minutes
Budgeting for education construction projects is no small task. For schools operating within tight financial constraints, careful cost planning can make the difference between...
This website uses cookies to improve your experience. We'll assume you're ok with this, but you can opt-out if you wish.AcceptRead More
Privacy & Cookies Policy
Privacy Overview
This website uses cookies to improve your experience while you navigate through the website. Out of these cookies, the cookies that are categorized as necessary are stored on your browser as they are essential for the working of basic functionalities of the website. We also use third-party cookies that help us analyze and understand how you use this website. These cookies will be stored in your browser only with your consent. You also have the option to opt-out of these cookies. But opting out of some of these cookies may have an effect on your browsing experience.
Necessary cookies are absolutely essential for the website to function properly. This category only includes cookies that ensures basic functionalities and security features of the website. These cookies do not store any personal information.
Any cookies that may not be particularly necessary for the website to function and is used specifically to collect user personal data via analytics, ads, other embedded contents are termed as non-necessary cookies. It is mandatory to procure user consent prior to running these cookies on your website.